KDHE New Health and Environment Laboratory
Public Hearing:  Not Required.  Legislation included Construction Management at Risk as the project delivery method.
Statement of Qualifications Due Date:  February 25, 2022
Advertisement in Kansas Register
Preliminary Program
List of Nominated firms:  McCown Gordon, McCarthy, Whiting-Turner, JE Dunn, GE Johnson
Milestone Dates for RFP    
    Pre-Proposal Meeting:   Tuesday, March 22, 2022 - 10:30 am
    Questions Due: Tuesday, March 29, 2022
    Answers and Final Addendum:  Friday, April 1, 2022
    RFP closing Date:  Friday, April 8, 2022 - 2:00 pm
Interview Date:  Tuesday, April 19, 2022
Firm Selected:  McCownGordon
 
WSU Marcus Welcome Center
Public Hearing:  March 9, 2022
Statement of Qualifications Due Date:  March 18, 2022
Advertisement in Kansas Register
Preliminary Program
List of Nominated firms:  McCownGordon, JE Dunn, Dondlinger & Sons, Hutton Construction
Milestone Dates for RFP    
    Mandatory Pre-Proposal Meeting:  April 21, 2022 at 11:00 am
    Questions Due:  May 5, 2022 End of Business
    Answers and Final Addendum:  May 12, 2022End of Business
    RFP closing Date:  May 19, 2022 at 2:00 pm
Interview Date: 
Firm Selected: 
KSU Seaton West 2nd Floor Renovation
Public Hearing:  June 13, 2022
Statement of Qualifications Due Date:  July1, 2022

Advertisement in Kansas Register
Preliminary Program
List of Nominated firms: GE Johnson, Hutton, McCownGordon, BHS Construction
Milestone Dates for RFP
     Pre-Proposal Meeting: July 20, 2022
     Questions Due: July 27, 2022
     Answers due from Owner-OFPM via addendum: August 3, 2022
     Date of Final Addendum: August 3, 2022
     Technical Proposals Due to OFPM:  August 10, 2022
Interview Date:  Interviews August 18, 2022
Firm Selected: 
KU 11th & Mississippi, Landscape Zone U (A-014692)

Public Hearing:  December 14, 2022

Statement of Qualifications Due Date:  January 13, 2023

Advertisement in Kansas Register

Preliminary Program

List of Nominated firms: JE Dunn + lark Construction, Turner Construction, Manhattan Construction Co.

Milestone Dates for RFP
     Pre-Proposal Meeting: March 13, 2023
    Questions Due:  March 16, 2023
    Answers due from Owner-OFPM via addendum:  March 21, 2023
    Date of Final Addendum:  April 3, 2023
    Technical Proposals Due to OFPM:  April 3, 2023
    Cost Proposals Due to OFPM:  April 3, 2023

Interview Date:  April 3, 2023

Firm Selected: 

KSU Global Center for Grain & Food Innovation (A-014699)

Public Hearing:  January 11, 2023

Statement of Qualifications Due Date: 

Advertisement in Kansas Register:January 26, 2023

Preliminary Program

List of Nominated firms:  GE Johnson, McCownGordon, Hutton Construction, Whiting Turner

Milestone Dates for RFP
     Pre-Proposal Meeting:   March 14, 2023
    Questions Due: March 16, 2023
    Answers due from Owner-OFPM via addendum:  March 23, 2023
    Date of Final Addendum:  March 21, 2023
    Technical Proposals Due to OFPM:  March 28, 2023
    Cost Proposals Due to OFPM:    March 28, 2023

Interview Date:  Mrch 31, 2023

Firm Selected: 

WSU-KUMC Health Sciences Educational Center

Public Hearing:  January 11, 2023

Advertisement in Kansas Register:  April 6, 2023

Statement of Qualifications Due Date:  April 21, 2023

Shortlist Date:  May 10, 2023

Preliminary Program

List of Nominated firms: McCownGordon + Dodnlinger, Nabholtz Construction, JE Dunn + Hutton

Milestone Dates for RFP
     Pre-Proposal Meeting: May 19, 2023
    Questions Due: May 30, 2023 at 2:00 pm
    Answers due from Owner-OFPM via addendum: June 6, 2023
    Date of Final Addendum: June 14, 2023
    Technical & Cost Proposals Due to OFPM:  June 21, 2023

Interview Date:  June 27, 2023

Firm Selected: 