Public Hearing: December 14, 2022
Statement of Qualifications Due Date: January 13, 2023
Advertisement in Kansas Register
List of Nominated firms: JE Dunn + lark Construction, Turner Construction, Manhattan Construction Co.
Milestone Dates for RFP
Pre-Proposal Meeting: March 13, 2023
Questions Due: March 16, 2023
Answers due from Owner-OFPM via addendum: March 21, 2023
Date of Final Addendum: April 3, 2023
Technical Proposals Due to OFPM: April 3, 2023
Cost Proposals Due to OFPM: April 3, 2023
Interview Date: April 3, 2023
Firm Selected: Turner Construction